Construction of the Paul Walker Pro Shop began in April 2026, and significant progress has been made since the project’s start. As of October 2026, asbestos remediation and demolition are complete, along with the CMU block walls, roofing, framing, and concrete flooring. Plumbing and electrical work are currently underway, and stone masonry has begun.
The project remains on schedule, with completion anticipated in April 2027. We are excited to see this project continue to take shape and look forward to sharing the finished facility with the Bowling Green community!